Case Study – Ardmore
Client: Ardmore
Job: Builders Cleaning, Sparkle Cleaning, Final Clean
Site address: Sparta Street, London, SE10 8DT
FastKlean were awarded the after builders contract for Heathbridge, following successful submission of PQQ, tender and negotiation for the contract.
The contract to supply cleaning services to cover:
- Builders Cleaning
- Sparkle Cleaning
- Final Clean
The site was a new residential build project and consisted of 1 bed, 2 bed, 3 bed and 4 bed apartments with communal areas.
The project duration 10 months.
This project was particularly demanding and required constant supervision and management, at times FastKlean local management was dealing with up to 8 site managers on a daily basis. Each site manager would have their own schedule and required works to be completed.
Schedule changes would occur on a daily basis so flexibility in approach as well as organisation of the cleaning team was paramount.
Working with other trades was required to get the job done, whilst also standing firm on our own requirements to be able to deliver our quality service.
Local management was on site daily, liaising with the client, organising staff, chasing schedules, chasing payments and forwarding suggestions for best working practice to ensure completion of works.
FastKlean were unable to retain all cleaners that started on the project, mainly due to the extreme conditions of the site and due to the ever changing schedule. However replacement cleaners were brought in to maintain numbers on site maintaining continuity and service delivery.
The contract came to a successful conclusion 3 months over schedule(client side) with all plots and communal area cleaned and signed off.